FUKUSHIMA, Japan — Officials raced Monday to restore electricity to Japan’s leaking nuclear plant, but getting the power flowing will hardly be the end of their battle: With its mangled machinery and partly melted reactor cores, bringing the complex under control is a monstrous job.

Restoring the electricity to all six units at the tsunami-damaged complex is key, because it will, in theory, power up the maze of motors, valves and switches that help deliver cooling water to the overheated reactor cores and spent-fuel pools that are leaking radiation.

Ideally, officials believe it should only take a day to get the Fukushima Dai-ichi nuclear plant under control once the cooling system is up and running. In reality, the effort to end the crisis is likely to take weeks.

Late Monday night, the deputy director general of Japan’s nuclear safety body suggested to reporters why there is so much uncertainty about when the job will be finished.

“We have experienced a very huge disaster that has caused very large damage at a nuclear power generation plant on a scale that we had not expected,” said Hidehiko Nishiyama of the Nuclear and Industrial Safety Agency.

The nuclear plant’s cooling systems were wrecked by the massive earthquake and tsunami that devastated northeastern Japan on March 11. Since then, conditions at the plant have been volatile; a plume of smoke rose from two reactor units Monday, prompting workers to evacuate.

Advertisement

‘STAYING WITH THE GAME PLAN’

In another setback, the plant’s operator said Monday it had just discovered that some of the cooling system’s key pumps at the complex’s troubled Unit 2 are no longer functional — meaning replacements have to be brought in. Tokyo Electric Power Co. said it had placed emergency orders for new pumps, but how long it would take for them to arrive was unclear.

If officials can get the power turned on, get the replacement pumps working and get enough seawater into the reactors and spent-fuel pools, it would only take a day to bring the temperatures back to a safe cooling stage, said Ryohei Shiomi, an official with the Nuclear and Industrial Safety Agency.

And if not?

“There is nothing else we can do but keep doing what we’ve been doing,” Shiomi said.

In other words, officials would continue dousing the plant in seawater — and hope for the best.

Advertisement

An official of the U.S. Nuclear Regulatory Commission said in Washington that Units 1, 2 and 3 have all sustained damage to their reactor cores, but that containment is intact. The assessment dispels some concerns about Unit 2, where an explosion damaged a pressure-reducing chamber around the bottom of the reactor core.

“I would say optimistically that things appear to be on the verge of stabilizing,” said Bill Borchardt, the commission’s executive director for operations.

Monday’s evacuation of workers from the plant came after smoke began rising from the spent-fuel storage pool of the plant’s problem-plagued Unit 3, Tokyo Electric spokesman Hiroshi Aizawa said. Unit 3 also alarmed plant officials over the weekend with a sudden surge of pressure in its reactor core.

What caused the smoke to billow first from Unit 3 and then from Unit 2 is under investigation, nuclear safety agency officials said. In the days since the earthquake and tsunami, both reactors have overheated and experienced explosions. Workers were evacuated from the area to buildings nearby, though radiation levels remained steady, the officials said.

‘PLEASE DO NOT OVERREACT’

Problems caused by the disaster have ranged far beyond the shattered northeast coast and the wrecked nuclear plant, handing the government what it has called Japan’s worst crisis since World War II. Rebuilding may cost as much as $235 billion. Police estimate the death toll will surpass 18,000.

Advertisement

Traces of radiation are tainting vegetables and some water supplies, although in amounts the government and health experts say do not pose a risk to human health in the short term. That has caused the government to ban the sale of raw milk, spinach and canola from prefectures over a swath from the plant toward Tokyo. The government has just started to test fish and shellfish.

Tokyo Electric said radioactive iodine about 127 times normal levels and radioactive cesium about 25 times above the norm were detected in seawater 100 yards off the Fukushima nuclear plant.

Despite that concentration, a senior official at the International Atomic Energy Agency said the ocean was capable of absorbing vast amounts of radiation with no effect and that — comparatively — the radioactivity released so far by the plant was minor.

“I would stress that the levels concerned are really very, very small, compared to the natural radioactivity that you find in the oceans,” said Graham Andrew, senior adviser to IAEA chief Yukiya Amano. “The quantities are tiny compared to the reservoir of natural radioactivity in the oceans.”

The Health Ministry has advised residents of Iitate, a village of 6,000 people about 19 miles northwest of the plant, not to drink tap water due to elevated levels of iodine. Ministry spokesman Takayuki Matsuda said iodine three times the normal level was detected there — about one-26th of the level of a chest X-ray in 1 liter of water.

“Please do not overreact, and act calmly,” chief Cabinet spokesman Yukio Edano said in the government’s latest appeal to ease public concerns. “Even if you eat contaminated vegetables several times, it will not harm your health at all.”

Advertisement

Edano said Tokyo Electric would compensate farmers affected by bans on milk, spinach and canola.

U.S. ISSUES POTASSIUM IODIDE

The World Health Organization said Japan will have to do more to reassure the public about food safety.

“Walking outside for a day and eating food repeatedly are two different things. This is why they’re going to have to take some decisions quickly in Japan to shut down and stop food being used completely from zones which they feel might be affected,” WHO spokesman Gregory Hartl said.

In a travel warning, the U.S. State Department offered potassium iodide to its staff in Japan as a precaution but advised its employees to refrain from taking the compound at this time. The government says it is making potassium iodide available “out of an abundance of caution” to its personnel and family members, and the compound should only be consumed after specific instruction from the U.S. government.

The troubles at Fukushima have in some ways overshadowed the natural catastrophe, threatening a wider disaster if the plant spews more concentrated forms of radiation than it has so far.

Advertisement

The nuclear safety agency and Tokyo Electric reported significant progress over the weekend and Monday. Electrical teams, having finished connecting three of the plant’s six units, were working to connect the rest by today, the utility said.

Once done, however, pumps and other equipment have to be checked — and the reactors cleared of dangerous gas — before the power can be restored. For instance, a motorized pump to inject water into Unit 2’s overheated reactor and spent-fuel storage pool needs to be replaced, said Nishiyama, the official with NISA.

The World Bank said in a report Monday that Japan may need five years to rebuild from the disaster, saying the cost to private insurers will be up to $33 billion and that the government will spend $12 billion on reconstruction in the current national budget and much more later.

 


Only subscribers are eligible to post comments. Please subscribe or login first for digital access. Here’s why.

Use the form below to reset your password. When you've submitted your account email, we will send an email with a reset code.