SCARBOROUGH – Baseball Hall-of-Famer Yogi Berra once stated, “It’s like deja vu all over again.”

This quote is very applicable to the latest proposed referendum question for the Wentworth Intermediate School.

Five years ago, a $38.3 million ballot question was overwhelmingly rejected by the voters. The $39.1 million proposal on the November ballot may suffer a similar fate — because, once again, the size proposed clearly exceeds the need.

The proposal is for a 163,000-square-foot building for 800 students. This results in 203 square feet per student. The state requirement, as per the Department of Education, for these grade levels is 125 square feet per student.

And the 15th Annual Construction Report published in School Planning and Management documents the national median is 125 square feet per student at these grade levels.

Did anyone on the design team think to ask why Scarborough needs a school that has 78 more square feet per student (62 percent higher) than the state requirement and the national median?

Advertisement

These are tough economic times. Folks are having trouble paying their bills and/or maintaining employment. The town of Scarborough recently invested $26.9 million in the Scarborough High School addition/renovation.

Every dollar of this amount comes from the pockets of Scarborough taxpayers, which makes it the most expensive locally funded project in the history of the state of Maine.

The town can ill afford to support a project that appears to be cost prohibitive ($66 million combining principal and interest), as well as for a building that is far beyond the needs of the community.

I don’t think there is much debate that Wentworth Intermediate School should be replaced at some point. That said, the state Department of Education earlier this year released its priority list for school construction projects.

There are 71 projects listed. Wentworth is not even on the list.

Did the school district even apply for state aid? If not, then why not? The fact is Wentworth was ranked 51st (out of 66) on the previous state list.

Advertisement

One would think if the need is so great, then the state would have had Wentworth ranked much higher on the list.

Another issue of concern is the removal of the athletic field and some parking from the proposal.

These items are part of the project and would likely be funded in later capital budgets.

This appears to be a clever way of lowering the cost — except that it doesn’t lower the cost.

It merely moves these inevitable costs to another area of the town budget, which appears to be a bit disingenuous.

The district is also adding significant cost to the project for geothermal heating.

Advertisement

Westbrook Middle School, designed by the same architects (Harriman), has geothermal heating, which isn’t working properly and already needs to be repaired even though the building is barely one year old, according to a recent article in The Portland Press Herald.

The voters rejected the 2006 proposal, which was for a building with 197 square feet per student.

The vote was “yes” 3,316 (39 percent) and “no” 5,176 (61 percent). That proposal was in a robust economy.

This proposal is for 203 square feet per student in an economy teetering on recession.

I would suggest a “no” vote on this ballot question, and I would advise the school district to bring a more modest proposal to the table next time around that meets the basic needs of our young people.

A more modest proposal, at least 33 percent less than the current one, would seem to strike a better balance between the needs of the school district and affordability to the taxpayers.

– Special to the Press Herald

 