ARA, Panama — The first test runs along the newly expanded Panama Canal began Thursday as tugs nudged the bulk cargo carrier Baroque into the first level of locks on the Atlantic side of the canal.

The expanded locks have increased the technical difficulty of maneuvering larger ships through the canal. But some of the challenges were eased by the weather during the test run, with it being a sunny day without much wind.

And the Baroque, at 836 feet in length, is not as big as the New Panamax behemoths, which measure up to 1,200 feet and which will begin transiting the waterway when it is opened.

The Baroque, rented for the operation, wasn’t carrying cargo on the first run through the Agua Clara locks, which took about three hours.

“The test went very well,” said engineer Giuseppe Quarta of Salini Impregilo, one of the firms contracted to build the expansion. “Today, we weren’t worried about the time.”

The formal opening of the expanded canal is set for June 26, 18 months behind schedule.

The $5.25 billion expansion is expected to double the canal’s capacity, tap new markets such as liquid natural gas shipments and cut global maritime costs by $8 billion a year.

Under the new system, tugboats have to engage in tricky maneuvers in a confined space inside the locks themselves to keep the bulky New Panamaxes from banging into the walls or even crushing the tugs if they lose control.


Only subscribers are eligible to post comments. Please subscribe or login first for digital access. Here’s why.

Use the form below to reset your password. When you've submitted your account email, we will send an email with a reset code.