Judge rules against rezoning Portland West End church

The city has yet to decide whether to appeal the decision, and the developer will let the city take the lead on the case, a spokesperson says.

By Randy Billings rbillings@pressherald.com
Staff Writer

A judge has ruled that the Portland City Council erred in 2012 when it rezoned the site of a historic church in the West End so the building could be used as office space.

Today's poll: Williston West Church

Do you agree with a judge's ruling that Portland City Council erred in rezoning the Williston West Church to be used for office space?

Yes

No

View Results

click image to enlarge

The Williston-West Church on Thomas Street in Portland.

2012 file photo by John Patriquin / Staff Photographer

click image to enlarge

Frank Monsour, owner of the Williston-West church building, stands in the sanctuary. Monsour has wanted to use the Parish House as the U.S. headquarters for his technology development startup, Majella Global Technologies.

2012 file photo by Gordon Chibroski / Staff Photographer

Additional Photos Below

Related Documents

Read the court order

Superior Court Justice Joyce Wheeler ruled last week that the rezoning, which many residents opposed, was not consistent with the city’s comprehensive plan, which guides development throughout the city.

The Williston-West Church was purchased in 2011 by Frank Monsour, an Australian businessman who wants to use the parish house as the U.S. headquarters for his technology development startup, Majella Global Technologies.

Offices, other than small home offices, are not allowed in Portland’s residential zones. In 2012, the council voted 6-3 to rezone 32 Thomas St., with conditions, so Monsour and his family could convert as much as 2,800 square feet of the parish house into office space for as many as 14 employees, who would park elsewhere.

A dozen West End residents appealed the council’s decision to Cumberland County Superior Court.

Monsour has already done some work on the church, and Majella Global Technologies’ website lists the property as its U.S. headquarters.

City attorney Danielle West-Chuhta said the judge’s decision was “disappointing” and the city is still considering whether to appeal.

The city’s comprehensive plan says that businesses in residential zones are supposed to serve the needs of the neighborhoods. An office does not fit that description, Wheeler ruled.

The judge also rejected the city’s argument that the project would foster economic development, since the business was already in the commercial district of Congress Street. Majella Global Technologies leased office space previously in the Time and Temperature Building downtown.

The council concluded that the new use of the church was needed to generate revenue to restore the building, which is on the National Register of Historic Places. But Wheeler ruled that the historic nature of the church would have been preserved through the city’s historic preservation ordinance.

Bruce McGlauflin, the attorney who represented the residents, said the ruling should be a warning to municipal councils and planning boards that loosely interpret their state-mandated comprehensive plans to justify development.

“There’s been a lot of cases out there where it seems like the courts are just eager to just rubber-stamp a city council decision to rezone, and this decision by the court clearly puts strength and meaning” back into the comprehensive plan, McGlauflin said.

‘MIDTOWN’ OPPONENTS BOLSTERED

The ruling has bolstered opponents of the “midtown” development proposed in Bayside. The proposal, which will go before the Planning Board next week, calls for four high-rise towers and two parking garages, which opponents say don’t comply with the city’s comprehensive plan.

Peter Monro, a co-founder of the Keep Portland Livable group, said in a prepared statement that Wheeler’s ruling sends “an important message” to city officials.

“It’s clear that the city continues to make arbitrary and inconsistent decisions in favor of development while ignoring not only the concerns of taxpayers and residents but also the planning process and its own regulations,” Monro said. “When is the city going to start listening to its residents instead of large, out-of-state developers whose interest is only in their bottom line, not in ensuring that Portland remains a special community where people can live, work and raise a family?”

According to city records, the Monsours received a building permit to renovate the first floor of the Williston-West parish house as office space and stabilize the bell tower. That work cost about $34,000.

On Monday, the company’s website listed 32 Thomas St. as the address of its U.S. headquarters, but most of the employees of the fledgling software company are working from home, said Mary Costigan, a former city attorney who represents the Monsours.

(Continued on page 2)

Were you interviewed for this story? If so, please fill out our accuracy form

Send question/comment to the editors


Additional Photos

click image to enlarge

The Williston-West Church on Thomas Street in Portland was bought by an Australian businessman to use as his company headquarters.

Jill Brady/Staff Photographer

  


Further Discussion

Here at PressHerald.com we value our readers and are committed to growing our community by encouraging you to add to the discussion. To ensure conscientious dialogue we have implemented a strict no-bullying policy. To participate, you must follow our Terms of Use.

Questions about the article? Add them below and we’ll try to answer them or do a follow-up post as soon as we can. Technical problems? Email them to us with an exact description of the problem. Make sure to include:
  • Type of computer or mobile device your are using
  • Exact operating system and browser you are viewing the site on (TIP: You can easily determine your operating system here.)


Today's poll: Williston West Church

Do you agree with a judge's ruling that Portland City Council erred in rezoning the Williston West Church to be used for office space?

Yes

No

View Results