Offshore-wind power prospects re-energized in Maine

The PUC approves a power contract for a pilot project off Maine, a key step after efforts were sidetracked.

By Tux Turkel tturkel@pressherald.com
Staff Writer

HALLOWELL — After months of uncertainty, Maine is back in the offshore wind energy game.

Today's poll: Wind farm grant

Are you in favor of a federal Department of Energy grant that would allow Maine Aqua Ventus to build a full-scale, pilot wind farm off Monhegan Island by 2016?

Yes

No

View Results

click image to enlarge

The project approved by regulators Tuesday builds upon technology behind a wind turbine called VolturnUS, above, that the University of Maine launched off Castine in June. The 65-foot-tall prototype is one-eighth the size of a full-scale turbine.

Gordon Chibroski/2013 Press Herald file

click image to enlarge

The planned site for an offshore wind pilot project is in the sea off Monhegan Island.

Courtesy of Maine Aqua Ventus

The Maine Public Utilities Commission voted Tuesday to approve a power-purchase contract for a pilot project that advocates hope will set the stage for a deep-water wind power industry that could eventually create thousands of jobs and billions of dollars in spending.

The 2-1 vote was critical to the Maine Aqua Ventus pilot project’s ability to move forward. This spring, the federal Department of Energy will decide whether the technology behind it is innovative enough to warrant a $46 million grant aimed at creating large wind farms, far out at sea, that can produce power at competitive rates.

Maine Aqua Ventus is being proposed by Maine Prime Technologies, a for-profit spinoff that represents the University of Maine and two general partners: Maine-based Cianbro Corp. and Emera Inc. of Nova Scotia, which owns the two largest utilities in northern and eastern Maine.

In May, the partners launched a one-eighth-scale model of a floating turbine off Castine. The unit is made of advanced composite materials designed to fight corrosion and reduce weight. Its hull is made of concrete, which can be produced in Maine and has a longer life span in the ocean than steel.

The prototype is now generating a small amount of power and collecting information. It already has endured extreme sea and wind conditions.

If they win the federal grant, the developers plan to build a full-scale, pilot wind farm off Monhegan Island by 2016. It would consist of two turbines, each with a capacity to generate six megawatts. The project is expected to generate 43,000 megawatt-hours a year, enough to power 6,000 average homes.

It also would draw an investment of $120 million to $166 million and as many as 341 jobs, say the project developers. They say they will try to ease concerns, including the project’s impact on fishing and scenery, among some residents and visitors to Monhegan, and in the midcoast town of Bristol, where an undersea cable would come ashore.

“We’re very happy with the approval,” said Jeff Thaler, an assistant counsel at the University of Maine. “We now will continue discussions with the PUC staff and local interests to finalize the term sheet.”

In their deliberations, the three commissioners debated the merits of the project, including the role of government in economic development, the impact on ratepayers and the prospects of the pilot project leading to commercial-scale, floating wind farms.

All three acknowledged elements of risk. But the two who voted to approve the project, David Littell and Chairman Tom Welch, said the project meets the legal benchmarks of Maine’s four-year-old Ocean Energy Act, which was passed to encourage such development.

Commissioner Mark Vannoy offered a differing view. He applauded the project’s technical innovations but said he sees little chance in the foreseeable future that offshore wind power will become cost-competitive with conventional sources such as the most efficient natural-gas-fired plants.

The above-market rates needed to develop the project would add a small charge for 20 years to Central Maine Power Co. customers’ bills. The allocations among customer classes could change over time, but the latest estimate is that an average residential customer would pay an additional 73 cents a month, $8.70 in the project’s first year. That figure would rise slightly each year, based on a formula for inflation.

PHILOSOPHICAL SPLIT PERSISTS

The philosophical split on the panel was identical to the positions taken in January 2013, when the PUC voted by the same margin to approve a power-purchase contract for a similar project proposed by the Norwegian energy giant Statoil.

(Continued on page 2)

Were you interviewed for this story? If so, please fill out our accuracy form

Send question/comment to the editors




Further Discussion

Here at PressHerald.com we value our readers and are committed to growing our community by encouraging you to add to the discussion. To ensure conscientious dialogue we have implemented a strict no-bullying policy. To participate, you must follow our Terms of Use.

Questions about the article? Add them below and we’ll try to answer them or do a follow-up post as soon as we can. Technical problems? Email them to us with an exact description of the problem. Make sure to include:
  • Type of computer or mobile device your are using
  • Exact operating system and browser you are viewing the site on (TIP: You can easily determine your operating system here.)


Today's poll: Wind farm grant

Are you in favor of a federal Department of Energy grant that would allow Maine Aqua Ventus to build a full-scale, pilot wind farm off Monhegan Island by 2016?

Yes

No

View Results