For alternative energy producers, is it worth plugging in?

Questions about the adequacy of CMP's transmission grid – and the risk of losing so-called future capacity payments as a result – prompt questions on the part of several developers.

By Tux Turkel tturkel@pressherald.com
Staff Writer

(Continued from page 1)

click image to enlarge

click image to enlarge

Related headlines

AT A GLANCE

A determination that Central Maine Power Co.'s new transmission line can't handle additional, scheduled power at its Orrington connection has kept nine renewable power projects in eastern and northern Maine from seeking valuable capacity payments from the region's grid operator. These payments can determine whether existing projects are profitable, or whether new ones get built.

The nine identified by the Maine Public Utilities Commission are: Verso Paper's Bucksport biomass boiler; Black Bear Hydro Partners' dams in Stillwater and Orono; three of First Wind's proposed wind farm projects -- Bowers Mountain, Oakfield and Bull Hill; two existing First Wind projects -- Rollins and Stetson; and Quantum Utility Generation's proposed Passadumkeag Wind Park.

CMP is building or upgrading 500 miles of transmission lines and various substations from Orrington to the New Hampshire border in Eliot.

Responding to the issues raised by generators, CMP says the project will meet its primary goal of improving reliability. As a side benefit, it will aid wind developers in western Maine's mountains, where upgrades will reduce system congestion.

"This is a reliability project," said John Carroll, CMP's spokesman. "It was always understood that there were transfer limits (in Orrington), but we weren't trying to fix that problem."

After gaining PUC approval in 2010, CMP's president, Sara Burns, called the project a "state-of-the-art system that will serve the region's growing renewable energy sector and provide tremendous economic benefits for the state."

In considering big power lines, regulators weigh two issues: how much power the lines can carry, and the impact of carrying that power on the grid's stability.

One big improvement CMP is making will increase the system's "thermal loading," so the lines can physically handle more power and heat without sagging or melting. But upgrading thermal loading doesn't solve stability concerns on the rest of the grid.

An initial analysis by ISO-New England, CMP and a consultant working for CMP identified potential for trouble if the system had to handle more than 1,350 megawatts under certain conditions. Transferring the full capacity of existing renewable plants in Maine, plus some generators in New Brunswick, would already exceed that figure.

Utility grids set transfer limits to help maintain a consistent flow of electrons. They rely on safety devices to cut power flow, just like a home's circuit breaker, if unstable voltages threaten power plants and equipment, such as during high-stress conditions that might take place on a hot summer day. In a worst-case scenario, an unstable power flow in Maine could have a wide-reaching impact.

"One of the effects could be that Connecticut would go dark," said Tony Buxton, a Portland lawyer who represents large energy users in Maine.

One of Buxton's clients is Verso Paper Corp. The company is in the midst of overhauling a boiler at its Bucksport paper mill to burn biomass, and sought to qualify it to compete in ISO-New England's capacity market. But the grid operator performed an initial analysis of connecting the boiler and determined that Verso's $42 million project wouldn't qualify because of the transfer limits in Orrington.

That was unwelcome news at Verso. The company already has spent the money, according to Bill Cohen, a company spokesman. The inability to receive capacity payments will have a financial impact, he said, but he wouldn't say if it would make the project unprofitable.

"We're hopeful the parties will come together and find a solution," he said.

Verso's problem is shared by other Maine projects, according to the Maine PUC. In FERC documents, it noted that the delay had disqualified nine renewable projects from participating in this year's capacity auction.

Besides Verso, these projects include key ventures by First Wind, the state's leading wind developer. Among them is one of Maine's largest windpower proposals, the 150-megawatt Oakfield project in Aroostook County, which won state approvals in January.

Also included is the 60-megawatt Bowers Mountain project in Washington and Penobscot counties, which was rejected last month by state regulators but may be redesigned; and the 34-megawatt Bull Hill project in Hancock County, which has received construction financing.

Also named are existing First Wind projects that send power to the grid, but have not qualified for capacity payments. They include the 60-megawatt Rollins project in Penobscot County and the 83-megawatt Stetson project in Washington County.

First Wind declined the newspaper's request to comment last week on the issue. But in the filing at FERC, First Wind said ISO-New England's incomplete analysis isn't a good reason to disqualify a project.

Other projects that were disqualified last month include existing Black Bear Hydro Partners hydropower projects on the Penobscot River and the proposed Passadumkeag Wind Park in Penobscot County.

ISO-New England argues that if the Orrington interface continues to pose stability problems, transmission upgrades beyond CMP's project are needed to achieve reliable operation. It also contends that the capacity process isn't the appropriate way to identify "low-cost fixes" sought by the Maine PUC.

In March, FERC sided with ISO-New England. It agreed with the grid operator's assessment that Verso, the Maine PUC and First Wind "erred in their understanding of the benefit of the MPRP."

The FERC commissioners concluded: "As ISO-NE explains, the MPRP was designed to ensure the continued reliability of Maine's transmission system and its ability to serve load; it was not designed with the purpose or intention of increasing transfer capacity to a level sufficient for the Maine resources to qualify (for capacity payments)."

Staff Writer Tux Turkel can be contacted at 791-6462 or at: tturkel@pressherald.com

 

Were you interviewed for this story? If so, please fill out our accuracy form

Send question/comment to the editors




Further Discussion

Here at PressHerald.com we value our readers and are committed to growing our community by encouraging you to add to the discussion. To ensure conscientious dialogue we have implemented a strict no-bullying policy. To participate, you must follow our Terms of Use.

Questions about the article? Add them below and we’ll try to answer them or do a follow-up post as soon as we can. Technical problems? Email them to us with an exact description of the problem. Make sure to include: