MONTPELIER, Vt. – A select board chairman Friday defended the process that led to his town’s approval of a mountaintop wind project that some residents are fighting.

Testifying before Vermont utility regulators, Lowell Select Board Chairman Richard Pion said the ballot question put to voters at Town Meeting last year included mention of a $400,000 annual windfall the town would get from the Kingdom Community Wind project because it was germane, not because he thought it would sway them to vote yes.

Green Mountain Power Corp. and Vermont Electric Co-Op have proposed a $150 million project that would erect 20 or 21 400-foot-tall towers along 3.2 miles of ridgeline. The wind farm could generate enough electricity to power 20,000 households, according to Green Mountain Power officials.

The developers have promised the town of Lowell annual tax payments of $400,000 to $535,000 for the life of the project, and also plan a “Good Neighbor Fund” that would pay five surrounding towns a minimum of $10,000 a year for 10 years.

Lowell voters signed off on the project in a 342-114 vote last year, but it still needs the approval of the three-member Vermont Board of Public Service.

Since the town’s vote, residents opposed to the project have mounted an effort to block it, saying the mountaintop windmills would be noisy, unsightly and a scar on the Lowell Mountain Range’s pristine landscape.

Advertisement

On Thursday, the board opened a 12-day hearing aimed at deciding whether it’s in the public’s best interests to build it.

On Friday, Pion and an economist hired by the developers testified before the board, answering pointed questions from a lawyer representing the Lowell Mountains Group, a 200-member citizens group opposing the project.

Economist Thomas Kavet, testifying for the developers about the economic impact of the project, acknowledged that aesthetics can hurt tourism.

Pressed by lawyer Jared Margolis, who represents nearby towns Craftsbury and Albany, Kavet said it’s possible fewer new homes will be built in the area because people won’t want to live near the wind project.

Kavet also said the project will mean 700 jobs during construction, more than $2 million in state tax revenues and $15 million in “direct fiscal benefits” to the town of Lowell.

 


Only subscribers are eligible to post comments. Please subscribe or login first for digital access. Here’s why.