The following is a tentative schedule related to the surveying, design and construction for the Cape Elizabeth Sanitary Sewer Rehabilitation Project:

Aug. 12, 2005 Complete Survey of Northern Section

Sept. 2, 2005 Complete Survey of Elizabeth Park/Brentwood Section

Sept. 30, 2005 Complete Survey of Running Tide/Winding Way Area

July 8 – Oct. 28, 2005 Preliminary Design of Complete System

Sept. 2 – Oct. 28, 2005 Subsurface Ledge Investigation

Advertisement

Nov. 2, 2005 Neighborhood Meeting – Northern Cape Section

Nov. 9, 2005 Neighborhood Meeting – Central/Southern Cape Section

Nov. 1, 2005 – Jan. 27, 2006 Final Design of Complete System

Jan. 27, 2006 Completion of Construction Specifications

Feb. 7, 2006 All three sewer projects go out to bid

Feb. 28, 2006 Bid opening for the Northern Section

March 7, 2006 Bid opening for Elizabeth Park/Brentwood Section

March 14, 2006 Bid opening for Running Tide/Winding Way Area