JACKSONVILLE, Fla. (AP) — Two cooling towers – both well over the length of a football field – came tumbling down in seconds on Saturday in Florida as part of an effort to dismantle a power plant.
The identical, 462-foot towers were imploded at St. Johns River Power Park in Jacksonville. After counting backward to one, a large blast sent the towers to the ground amid wild cheers. A huge cloud of smoke and dust plumed out and engulfed nearby trees.
Jacksonville Electric Authority and Florida Power & Light contracted Total Wrecking & Environmental to handle the implosion of the cooling towers and demolition of the power park for $14.5 million. The project is expected to be completed in April 2020.
Preparation took about 10 weeks for the implosion. It was over in just more than 10 seconds. More than 1,500 pounds of dynamite and 12,000 linear feet of detonation were used.
The St. Johns River Power Park, a 1,264-megawatt, coal-fired electric plant, was closed in January.
Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.
We believe it's important to offer commenting on certain stories as a benefit to our readers. At its best, our comments sections can be a productive platform for readers to engage with our journalism, offer thoughts on coverage and issues, and drive conversation in a respectful, solutions-based way. It's a form of open discourse that can be useful to our community, public officials, journalists and others.
We do not enable comments on everything — exceptions include most crime stories, and coverage involving personal tragedy or sensitive issues that invite personal attacks instead of thoughtful discussion.
You can read more here about our commenting policy and terms of use. More information is also found on our FAQs.
Show less