More than 11,000 Central Maine Power customers in Cumberland County lost power for a few hours Saturday.
CMP
Millions of dollars in foreign campaign funds pour into Maine as lawmakers push to ban them
Lawmakers say they will try to override Gov. Janet Mills’ veto of the foreign spending ban, but it won’t prevent foreign-owned companies from pouring money into Maine politics this fall.
Here’s why electricity bills in Maine are getting more expensive this month
The Maine Public Utilities Commission explained some of the reasons for multiple rate changes that are beginning to impact customer bills.
Much debated hydropower transmission corridor to be renegotiated because of cost increases
Maine lifted its stop-work order nearly 2 months ago but construction has not yet resumed on the project.
Andrew Rabbe: Politicians shouldn’t control our power
This November, we are voting on the Pine Tree Power referendum — a proposal to seize the state’s utilities and create a state-run power authority. Take it from someone who worked for the government-owned electric utility on Long Island, New York: putting politicians in charge of the power grid is a really bad idea. I […]
Work on NECEC transmission line may begin again soon
The Department of Environmental Protection has lifted a stop-work order on the stalled power line project, which is backed by Central Maine Power affiliates.
Work can resume on CMP power-line project, jury rules
Construction of the 145-mile line through western Maine has been stalled since a 2021 voter referendum that opposed the $1 billion project.
Future of CMP power line corridor now rests in jury’s hands
Closing arguments in a civil trial focused on whether developers of the stalled 145-mile line sped up construction simply to gain legal rights to continue building.
Defense rests on day 6 of trial over fate of CMP corridor
Jurors heard more conflicting accounts of why construction work sped up on the electricity line, which is supported by Central Maine Power and would extend 145 miles through western parts of the state.
After 5 days of trial over CMP corridor, many questions remain
In a week of proceedings, the trial over the fate of the Central Maine Power-backed corridor has often involved debate around the type of construction work performed.