May 15, 2013

Big transformer headed to new Maine substation

The Associated Press

WINDSOR — State police will escort a 286-ton electrical transformer over the road from Searsport to the Central Maine Power's new Coopers Mills Road substation in Windsor.

The transformer is scheduled leave the Mack Point Marine Terminal in Searsport early Wednesday morning on a 16-axle tractor-trailer rig. The total gross weight of the truck and transformer assembly is 426 tons.

The new transformer is part of CMP's $1.4 billion upgrade of Maine's bulk power transmission system. Its delivery could take up to two days to complete.

The truck leaves Searsport at 5 a.m. Its first leg will take it south on U.S. Route 1 to Belfast.

Were you interviewed for this story? If so, please fill out our accuracy form

Send question/comment to the editors




Further Discussion

Here at PressHerald.com we value our readers and are committed to growing our community by encouraging you to add to the discussion. To ensure conscientious dialogue we have implemented a strict no-bullying policy. To participate, you must follow our Terms of Use.

Questions about the article? Add them below and we’ll try to answer them or do a follow-up post as soon as we can. Technical problems? Email them to us with an exact description of the problem. Make sure to include:
  • Type of computer or mobile device your are using
  • Exact operating system and browser you are viewing the site on (TIP: You can easily determine your operating system here.)