Saturday, May 25, 2013
PORTSMOUTH, N.H. — The new Memorial Bridge connecting New Hampshire to Maine is still scheduled to open to traffic this summer.

In this January 15, 2013 photo, the 1st section of the new Memorial Bridge is floated out into the Piscataqua River from the Portsmouth waterfront.
Archer Western Contractors and NHDOT
Contractor Archer Western has put into place the new south span and a concrete deck. It has started erecting the south tower.
Steel tower pieces made by Structural Bridge in Claremont are being erected piece by piece by a barge-mounted crane near the south span. That will take about month to complete.
Plans are for the north span to be completed in March and floated into place at low tide, using the same process as used for the south span.
While the bridge between Portsmouth and Kittery, Maine, would be open this summer, Archer Western says final work, including landscaping and cleanup, will take until the end of the year.
Tweet
Further Discussion
Here at PressHerald.com we value our readers and are committed to growing our community by encouraging you to add to the discussion. To ensure conscientious dialogue we have implemented a strict no-bullying policy. To participate, you must follow our Terms of Use.Questions about the article? Add them below and we’ll try to answer them or do a follow-up post as soon as we can. Technical problems? Email them to us with an exact description of the problem. Make sure to include: